How to Calculate Critical Path Float Early Start amp Late Start and Early Finish amp Late Finish

How to Calculate Critical Path Float Early Start amp Late Start and Early Finish amp Late Finish

How to Calculate Critical Path, Float, Early Start & Late Start, and Early Finish & Late Finish - Home Start Here Exam Study Notes… PMP FnAQ! Knowledge Areas… Project Management Concepts Integration Scope Schedule Cost Quality Resource Communications Risk Procurement Stakeholder Training Videos Learn ITTOs PMP Study tips, Techniques, Strategies Last Mile Prep Course Top Course Reviews… PM PrepCast & Simulator Reviews Agile PrepCast Review Free Resources Free PM PrepCast Free PMP Simulator – 1 Free PMP Simulator – 2 Free PMP Formula Guide Free CAPM Simulator Free Agile Prepcast Free Blogging Guide Offers I Recommend.. My Resource List PMP Simulator PM PrepCast Video Course Free: PMP Launchpad PMP Guide Free Consult PMP Lessons Learned CAPM… CAPM exam changes CAPM Guide Free CAPM simulator CAPM Video Course Full-length CAPM Simulator PMP Concepts How to Calculate Critical Path Float Early Start & Late Start and Early Finish & Late Finish by Shiv Shenoy 600shares WhatsApp Facebook Twitter Pinterest LinkedIn This is a part-post from Developing Project Schedule project management activity post. You will learn how to calculate critical path, float/slack, early & late starts, and early & late finishes of a network path in this article. For easier understanding this post is divided into four parts that can be navigable at the bottom of each part. I suggest you get yourself a cup of your favorite beverage (I was going to say Coffee), this one is going to be a long ride. ? As we saw in Developing Project Schedule project management activity, Critical path is made up of series of activities from beginning to the end, where each activity has a dependency over previous activity in such a way that delay in any one activity causes delay in all subsequent activities, causing the project to slip. Click here to get my PMP exam brain-dump for free. In other words, critical path is the longest path in your project’s schedule network diagram, and is the SHORTEST possible duration for the project. How to Calculate Critical Path Let us take a simpler example than John’s home construction example we saw in previous lessons. This project involves assembling a train set. Calculating Critical Path is a simple 4-step process. Step 1 Find Activities Activities for this project are as below (output from Define Activities process) – Assemble two-tier bridge Join winding tracks Assemble and add train station Place standalone items around Assemble and add construction site Join train engine and bogies Place the train on the track Start the engine and let it chug! Step 2 Build Schedule Network Diagram Sequence activities and build schedule network diagram (output from Sequence Activities process) . This is how it looks, with individual activity duration in minutes – Figure 2: Assemble train set – schedule network diagram Step 3 Find all Possible Paths Find all possible paths through the diagram, there are 3 in our case – A -> B -> F -> G -> H A -> B -> C -> D -> G -> H A -> B -> C -> E -> G -> H Step 4 Calculate Duration for Each Path Let us see the duration for each of these paths – A -> B -> F -> G -> H —> 10+20+4+2+2 = 38 minutes A -> B -> C -> D -> G -> H —> 10+20+5+10+2+2 = 49 minutes A -> B -> C -> E -> G -> H —> 10+20+5+2+2+2= 41 minutes The network path with longest total duration is the critical path! Critical path is the shortest duration required to complete the project successfully. In our example this is the second path: A -> B -> C -> D -> G -> H, which comes to 49 minutes. Figure 3: Assemble train set – Critical Path Note that sum of durations of all activities on critical path comes 49 minutes, and sum of duration of ALL activities on the project is much longer. If managed well, the whole project can be completed within the critical path’s duration. In the next page, let us see how to calculate Float for activities.. (please use the page numbered link below to navigate).. Download PMP Book For FREE: PMP Exam Prep: Master Your Integration Management ConceptsNarayan Shanbhag, PMP – make your PMP exam prep a simple & focused affairHow To Prepare For PMP Exam The Agile Way! – by Arindam Thakur, PMPPMP Practice Exams Contributed to 40% PMP Knowledge – Kasturi Murthy, PMP 1 2 3 4 Recommended by Google Danika October 4, 2021, 7:25 pm Majaliwa January 24, 2021, 11:19 pm Carol December 26, 2020, 12:35 am Daniel Keegan March 6, 2020, 9:45 pm Shiv Shenoy March 10, 2020, 4:39 pm Aljoker January 15, 2020, 10:59 pm Arvind December 9, 2019, 11:21 pm Dhiraj November 22, 2019, 3:01 pm Shiv Shenoy November 25, 2019, 1:59 pm Ken October 2, 2019, 6:29 pm Shiv Shenoy October 7, 2019, 3:31 pm Osagie March 23, 2019, 2:06 am Shiv Shenoy March 25, 2019, 6:45 am Joel February 24, 2019, 5:40 pm Shiv Shenoy February 27, 2019, 3:23 pm Pankaj April 28, 2017, 9:45 am Shiv Shenoy May 1, 2017, 6:25 pm Shannon February 5, 2017, 9:15 pm Shiv Shenoy February 6, 2017, 7:36 pm magy danny April 5, 2017, 1:45 pm Bernard Bartholomew January 21, 2017, 9:12 am M. Gibson January 10, 2017, 1:18 pm Bhushan April 11, 2016, 12:28 am Shiv Shenoy April 19, 2016, 12:34 pm MOHIT CHUGH November 17, 2015, 4:45 pm Shiv Shenoy November 18, 2015, 9:43 am Hamed Barhumi March 12, 2015, 2:54 pm Shiv Shenoy March 17, 2015, 5:49 pm khadar January 27, 2015, 12:19 am Shiv Shenoy January 27, 2015, 1:32 pm aaaaa December 27, 2014, 7:49 pm json crown October 27, 2014, 5:08 pm Shiv Shenoy October 27, 2014, 11:26 pm Nick August 27, 2014, 6:58 am Shiv Shenoy August 27, 2014, 4:31 pm 555PPS June 10, 2014, 10:21 am Shivshanker Shenoy June 10, 2014, 2:29 pm NOni May 31, 2014, 5:25 am base_speed April 8, 2014, 7:35 pm Shivshanker Shenoy April 9, 2014, 6:28 pm Tony July 13, 2016, 6:07 am Hello My name is Shiv Click here to know how you can save tons of time in preparing for PMP or CAPM exam, learn with fun, and pass the exam at first attempt... Useful Posts For You Liked this brain-friendly PMP video? Click to subscribe for free, to get more such PMP videos as I make them for you! Get Free PM PrepCast! Get FREE PMP course Today!
Share:
0 comments

Comments (0)

Leave a Comment

Minimum 10 characters required

* All fields are required. Comments are moderated before appearing.

No comments yet. Be the first to comment!

How to Calculate Critical Path Float Early Start amp Late Start and Early Finish amp Late Finish | Trend Now